Skip to content

Project
Overview

Revitalize the Rapids

Bringing the rapids back to the Grand River in a safe and environmentally responsible way requires careful planning and execution. Working closely with community partners, government agencies and river development experts, we are working to revitalize the 2.5 mile stretch of the Grand River.

The project has two components:

LOWER REACH

Project Area: Bridge Street to Fulton Street

The purpose of the project is to Restore the rapids, improve public safety, restore aquatic habitat diversity and suitability for native Great lakes fish and mussel species and enhance river access and use.

Construction funding comes from state and local government funding, private funding, and  $11,026,695 in Watershed Protection and Flood Prevention Program funding to support the Lower Grand River Habitat Restoration from the the U.S. Department of Agriculture; Natural Resources Conservation Service.

In February 2026 the City of Grand Rapids issued a construction contract to Taplin Inc. in the amount of $14,562,625.98 with total expenditures not to exceed $25,982,101. This amount includes the costs of the construction contract, previously authorized preconstruction and environmental professional services, previously authorized mussel relocation services, previously authorized Grand Rapids Whitewater capital, easements, permitting, testing, and monitoring, public information, construction phase services by RiverRestoration.Org LLC, construction phase services by Viridis, 2026 mussel relocation by BioSurvey Group, fish relocation by Encompass Socio-Ecological Consulting, administration, and an approximate twelve percent allowance for contingencies.

The design for the Lower Reach Project has occurred over many years with significant input and coordination with state and federal regulatory agencies. 

Lower Reach Design Highlights: 

  • Once constructed, four dangerous low-head dams will be removed from the river and there will be rapids in Grand Rapids once again.
  • The four low-head dams will be replaced with two channel wide grade control structures constructed of rock, boulder, and alluvium that replicate natural channel design principles desired by Michigan Department of Energy Great Lakes and Environment (EGLE) and the Michigan Department of Natural Resources (MDNR).
  • The design will incorporate over 125 scattered habitat boulders to improve aquatic habitat and flow diversity.
  • The habitat boulders will create whitewater and replicate the boulder strewn rapids historically believed to be present in the Lower Reach of the river.
  • Three j-hook structures have been incorporated into the design at the river edges to create segments of slower water to enhance river access and use.
  • The design will significantly improve fish passage and available spawning habitat in this reach of the river compared to the existing condition.
  • The project no longer contains the previously proposed “standing whitewater wave features,” however removing the dangerous dams will provide increased opportunities for recreational access and use. Angling, wading, tubing, canoeing, and kayaking opportunities will be enhanced. Whitewater paddling opportunities may exist at some river flows.
  • Boating anglers will still be able to navigate the river under similar water levels as they do with the existing stretch of the river.
  • The Sixth Street dam will not be impacted by the Lower Reach project. Future discussions on potentially removing the Sixth Street Dam will be led by the Great Lakes Fisheries Commission and there will be a separate environmental review and permitting process associated with that project.

All required State and Federal permits necessary for construction to begin have been secured by the City of Grand Rapids and Grand Rapids WhiteWater. 

Federal Approvals:

  • The U.S. Fish and Wildlife Service issued a Biological Opinion on August 14, 2024 indicating that effects of the proposed projection are not likely to jeopardize the continued existence of the federally endangered snuffbox mussel. The Biological Opinion outlines specific conservation measures that must be followed before, during, and after construction to reduce impacts to federally endangered species.
  • The Federal Emergency Management Agency (FEMA) reviewed the proposed project and issued a Conditional Letter of Map Revision (CLOMR) on December 11, 2024 indicating the project would not cause an increase in flooding or the need for additional changes to the flood insurance rate maps.
  • Due to federal funding from the Natural Resources Conservation Service (NRCS) under Public Law 83-566 regulations, a Watershed Protection Plan-Environmental Assessment (Plan-EA) was developed to identify and address potential environmental impacts resulting from the proposed project. The NRCS issued a Finding of No Significant Impact (FONSI) in January of 2026 and a formal funding agreement with NRCS was signed in May of 2026.

State of Michigan Approvals:

  • Following the required public notice and public comment period, EGLE issued a draft construction permit for the Lower Reach on December 20, 2024. A final EGLE permit was issued to the City of Grand Rapids on June 23, 2025.

In April of 2026, the City of Grand Rapids awarded a contract with the Taplin Group who will serve as the contractor for the project.

Ah-Nab-Awen Park will be the construction staging and access area for equipment to get into the river. Construction mobilization in the park began on May 18, 2026.

As a requirement of the State permit, construction cannot begin in the river until July 1, 2026 to ensure water levels at the Sixth Street Dam continue to block invasive Sea Lamprey.

The in-river construction is anticipated to take two construction seasons and conclude in the Fall of 2027 pending water levels and any weather delays. Construction activity in the river will pause over winter.  

Relocation of threatened and endangered mussels species was required prior to the start of construction. The project design has reduced the impacts to the endangered mussels to the greatest extent possible, but relocation was still required.

Relocating mussels prior to the start of construction will have the most ecological benefit for these species. Changes to in-stream habitat are anticipated to benefit threatened and endangered species, fish hosts, and other fish species.

Relocation of state threatened and federally endangered freshwater mussel species occurred in the Lower Reach Project Area during the summer of 2024. An area of 45,000 square meters, roughly the size of eight football fields, was searched and 9,040 mussels were relocated to other suitable habitat areas in the Grand River. This includes 6,933 common mussel species, 2,069 state listed species, and 38 federally endangered species.

UPPER REACH

Project Area: Ann Street-Bridge Street

The objectives of the Upper Reach project are to:

  • Address public safety hazards associated with risk of failure and the recirculating hydraulics at the Sixth Street Dam through removal or modification
  • Maintain effective sea lamprey barrier in the Grand River watershed through construction of purpose-build infrastructure(s)
  • Restore rapids
  • Provide fish passage and aquatic habitat enhancement target species, including threatened and endangered species.
  • Diversify recreational opportunities
  • Develop as aesthetically and functionally natural stream design as possible
  • Include safe river access
  • Protect critical infrastructure and maintain riverbed stability
  • Minimize safety risks associated with increases in flow velocities

The Great Lakes Fishery Commission (GLFC) will lead an Environmental Impact Study (EIS) process for the Upper Reach project to evaluate feasible alternatives for construction of a new barrier for invasive sea lamprey in the Grand River to replace the aging Sixth Street dam.

The EIS process originally kicked off in 2019 but was paused as the design and permitting efforts of the Lower Reach Project were delayed.

The Great Lakes Fishery Commission and the U.S. Army Corps of Engineers officially resumed the EIS process in the spring of 2026. A public scoping meeting was held on April 22, 2026 and a 30-day public comment period closed on May 22, 2026. A draft EIS is anticipated to be available in July 2027.  

The GLFC will be the ultimate decision-making authority on the type and location of the proposed new lamprey barrier in the Grand River. The GLFC has contracted with the U.S. Army Corps of Engineers to conduct the EIS process and evaluate all potential alternatives for the Upper Reach Project.

The City of Grand Rapids and Grand Rapids Whitewater will be involved in future conversations regarding the Upper Reach project to continue to achieve the river access and use goals outlined in many community led planning processes such as Green Grand Rapids, GRForward, the Parks and Recreation Strategic Master Plan, and to enhance ongoing investments in the Grand River Greenway.

One lamprey barrier alternative being considered, as originally proposed by GRWW and the City of Grand Rapids, is the construction of an Adjustable Hydraulic Structure to be located approximately one mile upstream of the existing 6th Street Dam. The EIS process will develop and evaluate multiple project design alternatives to meet the project objectives. 

Over $20 million dollars in federal funding for the construction of a new lamprey barrier in the Grand River has been identified and committed to the Great Lakes Fishery Commission to ensure international sea lamprey control objectives continue to be met on the Grand River. These federal dollars come from the Great Lakes Restoration Initiative funding as well as an appropriation in the GLFC annual budget. Additional public and private dollars will also be identified to support the future Upper Reach project.

The EIS process has been paused by the GLFC until the Lower Reach permit application is deemed administratively complete and likely to be approved.

Construction of the Upper Reach cannot begin until the Lower Reach construction is finished and the Upper Reach EIS process has been completed. A timeline for the Upper Reach EIS process is not currently available. 

Project Benefits

This work has important economic, environmental and recreational benefits.

Additionally, the project provides significant educational opportunities for young people in the fields of math, science, engineering, environmental resources management, public health/policy and more. In partnership with the Grand Rapids Public Museum and the Lower Grand River Organization of Watersheds we have hosted an annual Summer Science & Leadership Camp where the Grand River becomes an engaging outdoor classroom for two weeks.

Through an intentional outreach effort to embed equity and inclusion into all river revitalization efforts, the project is consistent with the City’s Master Plan and vision of the Grand River as a prominent feature that can enhance the quality of life for all.

Economic Benefits

Restoration of the Rapids has long been touted as the catalytic project for revitalizing and reimagining the Grand River corridor in downtown Grand Rapids. This project is expected to have a positive impact on commerce and will add to the vibrancy and vitality of our region.

Removing dangerous dams, and improving river access and use, will provide new business development opportunities and support existing businesses along and near the river. 

New Recreational
Opportunities

The proposed design will create greater water flow diversity and support many new recreation activities like paddle boarding, tubing, kayaking, canoeing, rafting, and angling without impeding existing fishing and boating activities. The proposed improvements will encourage recreation by enhancing the visual, aesthetic and audible experience near and along the river.

Accessible by foot, bike, bus and car, the project will create the closest and most accessible water recreation for Grand Rapids’ most diverse neighborhoods.

Improved
Environmental
Conditions

The project will safely provide greater public access to the Grand River and enhance the river’s ecosystem when compared to existing conditions.

The removal of safety risks caused by the four existing low-head dams

Improved fish passage hydraulics over existing conditions 

Gently sloping riffles and the addition of over 125 scattered habitat boulders will provide better fish passage and habitat diversity for fish and mussel species

The project is anticipated to have a positive impact on mussel species and mussel habitat, meaning that more mussels could eventually occupy this reach of the river someday. 

Using natural boulders, rock and cobble to construct the proposed improvements will contribute to the aquatic diversity of the Grand River. The pocket water, micro-eddies, seams, fast water and slow water created by the natural boulders and alluvium all contribute to improved oxygenation, macroinvertebrate habitat, and overall health of the river.